    Sequence/Chained Backup Assistance

    Scheduled Pinned Locked Moved Backup
    3 Posts 2 Posters 46 Views 2 Watching
    Loading More Posts
    • Oldest to Newest
    • Newest to Oldest
    • Most Votes
    Reply
    • Reply as topic
    Log in to reply
    This topic has been deleted. Only users with topic management privileges can see it.
    • L Offline
      Lulina
      last edited by

      Hi there

      As I understand it, Sequence backups still need the schedule of the existing backup jobs to run
      I have 3 backup jobs, their schedules were different in that they start at different times
      The first one in the chain started at midnight and its backup schedule was enabled
      The other two jobs disabled their schedules

      Expected (According to this thread)
      Backup A (which is enabled) will run
      Backup B (which is disabled) will run after Backup A
      Backup C (which is disabled) will run after Backup B

      Outcome:
      Only Backup A worked as expected while Backup B & C never ran at all

      Perhaps I misunderstood the thread. I kept the Sequence job as is but enabled the schedules for them all
      I figured the time of the schedules should not matter, as long as they are enabled, they should run in sequence

      Expected:
      Backup A (enabled, midnight) run first
      Backup B (enabled, midnight) will run after Backup A
      Backup C (enabled, midnight) will run after Backup B

      Outcome:
      All three backup jobs started at the same, hypervisor nearly died, I restarted xen-server service. Whoops

      My Goal:
      These backup jobs should run in this order
      Backup A - start at midnight
      Backup B - start after Backup A finishes
      Backup C - start after Backup B finishes

      Any suggestions on how I can accomplish the above with Sequence backups? Thank you 🙂

      1 Reply Last reply Reply Quote 0
      • florentF Offline
        florent Vates 🪐 XO Team
        last edited by

        Hi Lulina
        you need to disable the schedul on the backup job (but don't remove them)
        Then you schedule the sequence ,and backup A, B and C should run

        Note that if theses job uses the sam VM ( like a delta backup followed by a mirror to S3 ) , you should enabled " merge backup synchronously" option on the advanced tab of the first job

        L 1 Reply Last reply Reply Quote 1
        • L Offline
          Lulina @florent
          last edited by

          @florent
          Expected:
          Backup A (disabled) run first
          Backup B (disabled) will run after Backup A
          Backup C (disabled) will run after Backup B

          Outcome:
          All three backups ran in sequence as expected

          Thank you Florent for the help here 🙂