    This topic has been deleted. Only users with topic management privileges can see it.
    • olivierlambertO Offline
      olivierlambert Vates 🪐 Co-Founder CEO
      last edited by

      🍾

      F 1 Reply Last reply Reply Quote 0
      • F Offline
        flakpyro @olivierlambert
        last edited by flakpyro

        @florent updated my homelab XO instance this morning to try this out since its been merged. Seems like concurrency has changed if the field is left empty? It used to default to 2 but now i see it trying to back up every VM in the job at once? I dont think this is the case anymore, its just the completed tasks do not update their progress and clear properly.

        Under the "Backups" Tab in the XO the backup says successful, however none of the concurrent backup tasks have completed under tasks. Looking at the backup "Remote" storage i see it still appears to be writing data so perhaps the job is not actually complete as XO states. --This was the merge operation happening in the background as it turns out the job was actually complete however the tasks were not clearing.

        F 1 Reply Last reply Reply Quote 0
        • F Offline
          flakpyro @flakpyro
          last edited by flakpyro

          @florent Backup did seem to run however the tasks never cleared. I restarted the toolstack on both hosts which cleared the tasks.

          Set job concurrency to 2 manually on the job and ran it again. Once again the task list filled with all the VMs from the job at once, the job seems to process and succeed but the tasks never clear and you cant really tell whats happening since the task window becomes cluttered with VMs from the job with a random state of progress that never seems to clear on its own. I think ill have to roll back to a previous release for now. Hopefully this plan isn't to push this to the XOA appliance just yet!

          Stuck tasks:
          10ab8402-447e-4d4b-8155-7586661133bf-image.png

          Yet completed and successful job:
          d0515313-1e01-4c3f-8749-fb83f080a068-image.png

          1 Reply Last reply Reply Quote 0
          • A Offline
            Andrew Top contributor @florent
            last edited by

            @florent @olivierlambert Not good!... I reverted back due to problems.

            Replication does run. It seems to work. But it leaves lots of zombie export tasks, like:
            Exporting content of VDI ftp_root_jgfkd through NBD+CBT (on xcp1) 17%

            I get about 80% stuck tasks. A toolstack restart clears the tasks....
            CR settings: CBT enabled. NBD=2. Purge enabled.

            F 1 Reply Last reply Reply Quote 0
            • F Offline
              flakpyro @Andrew
              last edited by

              @Andrew I am having the exact same issue! Also rolling back! Glad its not just me haha

              A 1 Reply Last reply Reply Quote 0
              • A Offline
                Andrew Top contributor @flakpyro
                last edited by

                @flakpyro @florent I had the same problem with the test branch that did not get solved.

                1 Reply Last reply Reply Quote 0
                • florentF Offline
                  florent Vates 🪐 XO Team
                  last edited by

                  thabnks for the test
                  are you doing replication only ? or is a job doiing replication and backup ?

                  F A 2 Replies Last reply Reply Quote 0
                  • F Offline
                    flakpyro @florent
                    last edited by

                    @florent I am just running a "Delta Backup" to an NFS SR. I haven't rolled back yet so if there is any sort of logs i can provide let me know. This is my "home lab" at home where i test new versions of XOA and XCP-NG updates before we end up seeing new features in production with our full XOA appliance at work. 🙂

                    1 Reply Last reply Reply Quote 0
                    • A Offline
                      Andrew Top contributor @florent
                      last edited by

                      @florent The job is just Continuous Replication to another local host. These were normal hourly delta transfers.

                      1 Reply Last reply Reply Quote 0
                      • Tristis OrisT Offline
                        Tristis Oris Top contributor
                        last edited by

                        Same. Delta, 2 threads, 2 runing, but jobs not cleared.
                        b15d31c5-b0ad-407f-a1bc-b615510a9acf-image.png

                        1 Reply Last reply Reply Quote 0